Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

IMPACTS 01/30/23 Mission Daily Schedule

Plan of the Day for Monday, Jan 30, 2023
 
All times are in Eastern Standard Time (EST)
 
All -0900 Daily Weather Briefing
 
Wallops 
Monday, 30 January: Fly Day, Science Flight #7
0730  Aircraft access/power on
0800  Pilot’s science brief
0850  Planeside brief/doors close
0927  Takeoff
~1324  P-3 lands at WFF
L+15  Debrief
 
Tuesday, 31 January: No Fly Work Day
0830 – 1600  Access and power on the plane for instrument teams
 
Dobbins 
Monday 30 January: Fly Day, Science Flight #7
0430: Hands On
0530: Hands Off / Tow / Crew Brief – Hangar 5 Science Room 1026 and MS Teams
0840: Take Off
1410: Landing (Tentative)
1440: Debrief – Hangar 5 Science Room 1026 and MS Teams (info below)
 
Tuesday, 31 January: No Fly Work Day
0800 - 1600 Hands On / Aircraft Access
 
General announcements
Current health guidelines call for:
Wallops – No regulations
Dobbins – No regulations
 
Project Swag:  https://www.cafepress.com/IMPACTSShop
Field catalog with the tentative weekly schedule: http://catalog.eol.ucar.edu/impacts_2023
Project picture gallery (please contribute by uploading your project pictures).
Please complete the check-in form upon arrival at Wallops or Dobbins.