Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

DCOTSS 05/06/21 Mission Daily Schedule

0700 - 1500 ER2 Crew Support
 
Achievements and goals

  • All instruments made great progress towards the physical integration in the ER2 nose section.
  • PALMS
    • Mostly finished physical check fit; Tomorrow will reposition two components to eliminate physical interference.
    • Instrument power checks using the lab's 120V supply
    • Coordinate remote internet access to the instrument
  • POPS
    • Continue physical integration and plumbing
  • MMS
    • Finished ER2 nose section integration
    • Start work on the other MMS locations