Monday, September 11 Accomplishments
  • EMI Testing was completed by midday. No noise or interference was found.
  • Instrument teams made final preparations for Tuesday’s shake flight.
Tuesday, September 12 Plans
  • 06:00 - 06:20  PALMS laser gas servicing
  • 06:20 - 11:30  A/C access
  • 13:00  Lab meeting
  • 13:30  Egress training
  • 14:00  Takeoff for shake flight
  • There will be no a/c access after the completion of the shake flight.
Wednesday, September 13 Plans
  • 06:00 - 18:30  A/C access

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.