ATom 08/18/17 Mission Daily Schedule

Friday, August 18
All first wave instruments (NOyO3, QCLS, DLH, Picarro, TOGA, MMS, PALMS, AMP, ATHOS & SAGA), with the exceptioin of CAFS, installed
All power checks, with the exception of DLH, successfully completed
No issues

Saturday, August 19
First wave teams departed

Sunday, August 20
Second wave teams arrive

Monday, August 21
07:00        Badge office open for renewal of expired badges
06:00-15:00    A/C crew will work 9 hour days M-Th (Friday RDO)

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.