ATom Plan of the Day

Thursday, 7 July

  • Media Day
  • ARMAS installed and power check complete
  • PANTER/UCATS installed and power check complete
  • MMS essentially completed installation and power check complete
  • TOGA completed installation
  • ISAF mechanically installed
  • Aircraft fuselage pressure check complete
  • Aircraft weight and balance complete

Friday, 8 July

  • 06:30-17:30  Aircraft access
  • TOGA, ISAF and QCLS power checks

Upcoming:

  • 11 July: Shake down flight (ETD 10:00) (a/c access from 07:30 to 08:30 outside)
    •         Preflight briefing 08:30
    •         Doors closed 09:30
  • 12 July: Science Test Flight #1 (ETD 11:30)

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.