ATom 07/05/16 Mission Daily Schedule

Tuesday, 5 July

  • 0630 - 1730: Aircraft access
  • WAS snakes installed; leak check in progress
  • CAPS performing off-aircraft calibration

Wednesday, 6 July

  • 0630 - 1730: Aircraft access
  • AO2/Medusa returns to finalize instrument installation and perform power check
  • ISAF installation

Upcoming:

  • 8 July - Aircraft weight and balance

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.