Plan of the day for Monday, February 17
For the long-term (forecasting and science) tentative plans, please refer to the Daily Science plan.
Project website: https://espo.nasa.gov/impacts
Project data catalog: http://impacts.atmos.washington.edu/
T-Shirts!! Wallops: See Dan. Hunter: See Bernie
First time at Wallops? See Dan and Kelly for the safety briefing.
All times are EST
IMPACTS General
Monday, Feb 17
9:00 - 10:00: Daily Briefing (Wallops W162; Webex/Telecon)
Tuesday, Feb 18
9:00 - 10:00: Daily Briefing (Wallops W162; Webex/Telecon)
IMPACTS P-3 - Wallops
Monday, Feb 17
1000 - 1500 A/C Access
Tuesday, Feb 18
0800 - 1630 A/C Access
IMPACTS ER-2 - Hunter
Monday, Feb 17
0730 - 1530 A/C access
Tuesday, Feb 18
Science Flight - Details TBD, (see Daily Science Plan)
ESPO Crew on Deck
Wallops: Dan Chirica (650 318-8257), Caitlin Murphy (650-680-7732)
Hunter: Bernie Luna (650 417-8810)
IMPACTS Webex telecon : +844 467 4685 code: 804464#