Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

HS3 09/10/14 Mission Daily Schedule

Overview:  AV-6 Science Flight #5 is scheduled to takeoff today at 1800 EDT for a 25-hr flight into P29/91L. The disturbance is still unorganized, but it is expected by most models to consolidate and slowly intensify. The NHC gives a 20-70% chance of development into a TC in 2-5 days. 65 sondes are loaded for this flight.
 
Tentative schedule for next AV-6 flight would be takeoff Friday evening with P29/91L as the target again, although the local weather doesn’t look too promising.
 
Thur Sep 11 (Media Day)
WFF (EDT)
-  0800 Forecast Briefing (S115)
-  0930 COMSEC Brief
-  1900 (estimated) AV-6 Land
-  1930 Forecast Briefing (S115)
 
Fri Sep 12 (possible Science Flight #6 - time TBD)
WFF (EDT)
-  0800 Forecast Briefing (S115)
-  1100 AV-6 Instrument Postflight/Preflight for potential Fri evening flight
-  TBD  Science Flight #5 Debrief (S115)
-  1930 Forecast Briefing (S115)