Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

HS3 09/06/14 Daily Schedule

Overview:  AV-6 completed Science Flight #4 this morning (target I90L/P27L, 59 sondes dropped).  Engine nozzle change now in progress.  Next potential flight Tue Sep 9 (target P29L). 

                       

Sun Sep 7 (AV-6 Engine Nozzle Change)

WFF (EDT)

     -     0800 Forecast Briefing (S115)

     -     1930 Forecast Briefing (S115)

 

Mon Sep 8

WFF (EDT)

     -     0800 Forecast Briefing (S115)

     -     0830 Computer Scans (S217)

     -     0900 Instrument Preflight for potential Tue flight

     -     1030 Science Flight #4 Debrief (S115)

     -     1930 Forecast Briefing (S115)