ATom Plan of the Day
Tuesday, 8/2
ATom Plan of the Day
Tuesday, 8/2
ATom Plan of the Day
Monday, 8/1
ATom Plan of the Day
7/30, Saturday
7/31, Sunday
The Aircraft wash has been completed. The crew decided to tow the aircraft in due to the fires over the mountain.
We will plan to tow in to position for the outside test Monday morning. Still working details, on the side, for location and to limit any possible delays.
7/24 no Aircraft access other than servicing the CIT-CIMS instrument as planned.
Monday A/C access starts at 0700-1700.
Saturday 7/23
A/C out on wash rack to continue the wash
Sunday 7/24
A/C planned to remain outside in prep for Monday housekeeping/science system test
Monday 7/25
A/C located at wash rack and will be towed in after test, if possible, but may have to wait for SOFIA.
Access start at 0700
Access end at 1700
ATom Plan of the Day
A/C access for Tuesday (7/19) will be approx. 0700 to TBD
We originally were planning for a 1000 takeoff but due to pilot availability the morning is no longer an option. We are going to attempt and afternoon flight, time TBD after confirmations in the a.m.
Short summary story for flight today is the "hum" was still present, though it was not as prominent and had a few different characteristics which led to the removal of the SAGA chimney inlets and a blank off plate installed.
This is our next flight attempt for investigating the "hum".
ATom Plan of the Day
A/C access for Monday (7/18) will be approx. 1030 to 1500
We are planning a 0900 takeoff for the first t/s effort for the "hum" issue. Should only be an hour.
We will have details available following the flight and at 1300 on whether we will need a flight on Tuesday. If we do need to fly Tuesday we are planning two flights so access will be limited.
ATom Plan of the Day
A/C access for Saturday (7/16) will be for the CIT-CIMS servicing. No aircraft access. Mike Moore will assist the servicing at 0700.
Sunday (07/17) will be a NO A/C ACCESS and Dave Johnson will assist at 0700.
ATom Plan of the Day
Tuesday, 26 July
ATom Plan of the Day
Friday, 29 July
Saturday and Sunday there will be a/c access from 08:00 until 16:00. Monday there will be egress training at 05:00.