Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.
From: | KLFI | To: | KLFI | ||
---|---|---|---|---|---|
Start: | 06/03/14 19:20 Z | Finish: | 06/03/14 21:20 Z | ||
Flight Time: | 2 hours | ||||
Log Number: | 14B008 | PI: | Chris Hostetler | ||
Funding Source: | David Considine - NASA - SMD - ESD Modeling Analysis and Prediction | ||||
Purpose of Flight: | Science | ||||
Comments: | Instrument Check Flight for HSRL 1.1 and RSP installation in UC-12 in preparation for CALIPSO cal/val campaign in Bermuda. Crew was Kagey, Wusk, Harper, and Hare. |
14B008 | |
---|---|
Flight Hours Approved in SOFRS | 28 |
Total Used | 37.6 |
Total Remaining | -9.6 |
14B008 Flight Reports | ||||||
---|---|---|---|---|---|---|
Date | Flt # | Purpose of Flight | Duration | Running Total | Hours Remaining | Miles Flown |
06/03/14 | HSRL1.1 I 1401 | Science | 2 | 2 | 26 | |
06/05/14 - 06/06/14 | HSRL1.1 I 1402 | Science | 3.3 | 5.3 | 22.7 | |
06/09/14 | HSRL1.1 R 1403 | Science | 2.8 | 8.1 | 19.9 | |
06/10/14 | HSRL1.1 R 1404 | Science | 3.4 | 11.5 | 16.5 | |
06/12/14 | HSRL1.1 R 1405 | Science | 3.6 | 15.1 | 12.9 | |
06/12/14 | HSRL1.1 R 1406 | Science | 3.2 | 18.3 | 9.7 | |
06/14/14 | HSRL1.1 R 1407 | Science | 3.3 | 21.6 | 6.4 | |
06/14/14 | HSRL1.1 R 1408 | Science | 4.1 | 25.7 | 2.3 | |
06/16/14 | HSRL1.1 R 1409 | Science | 3.6 | 29.3 | -1.3 | |
06/18/14 | HSRL1.1 R 1410 | Science | 3.9 | 33.2 | -5.2 | |
06/19/14 | HSRL1.1 R 1411 | Science | 4.2 | 37.4 | -9.4 | |
06/19/14 | HSRL1.1 R 1411 | Ferry | 0.2 | 37.6 | -9.6 |